Boao Lecheng International Medical Tourism Pilot Zone Power Distribution Project

Project Background

Boao Lecheng International Medical Tourism Pilot Zone is a national-level medical special zone. It gathers a large number of medical institutions, healthcare and research buildings. These are medical Class I loads with stringent requirements for power supply continuity and safety. Situated in the tropical coastal region of Hainan, the area features year-round high temperature, high humidity and prominent salt-spray corrosion. As a green grid demonstration project, SF6-based equipment is completely banned here. Medical loads adopt zero tolerance for supply outages; an intelligent distributed self-healing system is required to achieve local fault isolation and rapid supply restoration to guarantee uninterrupted medical services.

Project Overview

• Procurement Date: August 2019 

• Project Location: Boao Lecheng International Medical Tourism Pilot Zone, Qionghai City, Hainan Province, China 

• Core Products: 12 kV ASNA Atmospheric Pressure Sealed Natural Air Insulated Switchgear 

• Application Scenarios: Distribution switching stations and outdoor cabinet-type distribution retrofit within the medical park 

• Total Supplied Units: 12 sets (116 units in total) 

• Manufacturing Lead Time: 30 days 

Gemini_Generated_Image_bi8ix1bi8ix1bi8i (1) (2)

Solution Description

The primary equipment adopts 12 kV ASNA Atmospheric Pressure Sealed Natural Air Insulated Switchgear. Cabinets utilize an enhanced anti-corrosion treatment, suited to coastal operating conditions with salt spray and high humidity. The automation system is fitted with an intelligent distributed self-healing control system. Switching units communicate on a peer-to-peer basis, enabling local fault detection, isolation of faulty sections and rapid supply restoration for fault-free segments, to minimize outage impacts on medical loads. Loop checks, interlock simulation and joint commissioning of self-healing logic are performed at the factory. On-site work is limited to positioning and cable termination. This allows commissioning within constrained power-cut windows and meets the medical park's requirements for a green, highly reliable and intelligent distribution network.

2 (26)
undefined

Specialized Manufacturing

  • Technical Alignment & Logic Confirmation:

Multiple rounds of technical discussions are held in the preliminary phase to confirm primary main-circuit parameters and enclosure anti-corrosion treatments. Joint validation focuses on the logic, communication interfaces and protection settings of the intelligent distributed self-healing system. Complete drawings and configuration packages are issued as deliverables. 

  • Production & Comprehensive Factory Acceptance Tests:

Manufacturing follows the approved drawings strictly. Enclosures and standard fasteners receive dedicated coastal anti-corrosion treatment. In addition to routine electrical tests, coordinated simulation testing of the distributed self-healing logic is performed. Line short-circuit and earth-fault scenarios are simulated to verify the full sequence of fault isolation and supply restoration. Shifting most commissioning work to the factory reduces on-site workload. 

  •  Delivery of Complete Technical Documentation & Specialized Training:

A full set of documentation — drawings, operation manuals and self-healing system commissioning guides — is supplied with the equipment. Specialized online and on-site technical training is available, covering equipment maintenance, routine checks of the self-healing system and fault handling procedures, to support customers with ongoing operation and maintenance. 


doc_img3

Project Outcomes

The project-specific products are purpose-built for the local high-temperature, high-humidity and heavy salt-spray environment. Since commissioning, enclosure surfaces and internal components have remained in sound condition, with no signs of corrosion or ageing. The intelligent distributed self-healing system operates reliably, carrying out local fault isolation and rapid supply transfer to prevent large-scale and prolonged outages triggered by line faults. The full assembly has endured the combined harsh conditions of Hainan's tropical coastal climate: high temperatures, high humidity, heavy salt spray and typhoons. Its performance meets the requirements for medical Class I load installations and has earned high recognition from the client.